In a press release, AFC General Secretary and former Minister of Public Infrastructure David Patterson says that the announcement on Tuesday that the government had terminated talks with the Chinese contractor and moved to the next bidder on the replacement of the Demerara Bridge was suspicious and requires a proper, detailed and coherent explanation.
In a statement today, Patterson said the initial reason given by Vice President Bharrat Jagdeo, that the financing costs were too high is rubbished by their project evaluation process, which the cabinet received and granted in a “no-objection” approval to the Ministry of Public Works to engage CSCECL from November 2021 based on a Design-Build-Finance (DBF) model.
“For the country to believe the Vice President now raises questions as to why in November he clearly stated that the financial terms and conditions would be no less favourable than those submitted in the preferred bidder’s price proposal and that the construction cost of US$256.6 million was the lowest among all bidders”, Patterson said.
Therefore, he said it was not credible for the sudden termination of negotiations because the financing costs were too high, and he further called on the engineering and financial advisers to speak on this questionable decision.
It is also no secret, he said, there is great suspicion that one of the contracts referenced by the interviewer is the proposed contract with CSCECL, and there is now a strong belief that the two events signal that there was more to the” mortar than the pestle”.
Comments
For once i have to admit i agree with the AFC, this government have no clue what they are doing, this is going to make it so easy for my people to win the next election. (drill and pump baby)